The first two boats are being built at the same time. Work began in October 2009 and will finish in time for the 2010 season and - for Boat 1 - for the Shetland Round Britain and Ireland Race. We hope! Most recent pictures at the top. Last updated 05.05.10.

 
These are the last images for this page - to keep up with the last stages of preparation, the launch and the race please click here      
                 

     
 
Topsides and inside have been painted, and bits are going in - sinks, anchor windlass, engines and systems for navigation among others. Launching is planned for May 15th ... Sailing for May 16th ... Qualifying May 17th-18th ...

                   
 
     
Boat 1 is fitting together nicely. Meanwhile, the coachroof and bridgedeck for Boat 2 are underway    
         
 
                   
     
               
           
                             
       

 
 
 
   
 
   

 
 
 
                                     
 
The coachroof moulding was released on Monday March 22nd, and taken out of the shed and turned over in preparation for being brought down to our yard the next day    
                 

 
 
All the bulkheads are in, we've got rudders - always useful in a race - furniture is in position and ready to be bonded, the engines are being installed and sound-insulated and the position of the spinnaker has been marked out ready for fitting
 
Vacuuming foam core to the coachroof moulding for Boat 1 - that's a lot of seals to check for leaks  
                 
       
           
 

       
                                   
     

           
                                   
                 
            Bulkheads going into Boat 1 and, left and above right, laminating the underside of the galley. Above, shaping the windows and the coachroof in its mould
                                   
     

           
                                   

 
         

 
Below and right: the coachroof plug released; above right: an engine bed; above left: locker lids under vacuum
 
         

 
 
Below: last stages of coachroof plug, which should be released on Feb 15th; above: midship sole in position in port hull, and beginning of mould for galley and saloon seating for Boat 1
 
 
                 
   
 
   
   
                       
         
 
                   
Near left and below: preparation of coachroof mould on Boat 2; above: glassing plug  
       
         

   
   
The coachroof, designed by Nic Bailey. is taking shape on Boat 2 and, right, Boat 2's transom steps
       
                             
               
                       
     
                 
     
         
               
  Hulls for Boat 2 laid up, completed and transported to their own shed for joining with the wetdeck. Above, strongback for wetdeck mould for Boat 1, and bulkheads going in
               
                               

  Laying up of glass and foam core for hull 1 of Boat 1 and, above, reinforced and complete          
   
 
         